DEVELOPMENT · RISK ENGINE
Development Risk Engine
Real-time risk intelligence across delays, contractors, permits, materials, labour, infrastructure and customer-facing milestones.
38 active risks22 delays · 5 overruns · 6 resource shortages · 4 critical estates
Total Risks
38
all severities
Delays
22
> 4 days
Budget Overruns
5
₦84M total
Resource Shortages
6
cement · power · labour
Permit Risks
7
FCT · Lagos · Enugu
Critical Estates
4
exec attention
+1 WoW
Risk category grid
Live category counts · severity · trend · estate exposure
Contractor risk
11
issues
+3 WoW
PH Marina · Enugu Skyline
Permit risk
7
issues
+1 WoW
Kuje Heights · Abuja Hills
Material risk
6
issues
+2 WoW
Magodo Vista · PH Marina
Labour risk
5
issues
0 WoW
Abuja Hills · Eko Bay
Weather risk
2
issues
-1 WoW
PH Marina · Eko Bay
Community risk
3
issues
+1 WoW
Kano Ridge
Utility risk
4
issues
+2 WoW
Ibadan Crest · Ibeju City
Compliance risk
4
issues
0 WoW
Enugu · Kuje Heights
Live development risk board
Sorted by severity · owner · recovery plan
| Estate | Risk | Type | Severity | Owner | Days slip | Exposure | Recovery plan | Action |
|---|---|---|---|---|---|---|---|---|
| PH Marina | Drainage delay | contractor | critical | Coastal Works | 18 | ₦42M | Replace contractor | Escalate |
| Enugu Skyline | Land prep behind | contractor | critical | Niger Build | 14 | ₦22M | Freeze payment | Review |
| Abuja Hills | Perimeter contractor | delay | high | Atlas Infra | 12 | ₦18M | Add crew | Approve |
| Eko Bay | Road rework | quality | high | Lagos Build | 6 | ₦14M | QA audit | Inspect |
| Magodo Vista | Cement supply | resource | high | Sahel Cement | 4 | ₦8M | Alternate supplier | Execute |
| Kuje Heights | Drainage permit | compliance | medium | FCT Office | 2 | permit gap | Legal follow-up | Track |
| Ibadan Crest | Transformer late | utility | medium | IBEDC | 8 | ₦6M | NERC liaison | Escalate |
| Kano Ridge | Community access | community | medium | Comm. rel. | — | goodwill | Town-hall meeting | Schedule |
Risk heat · estates × categories
PH Marina · Contract.
22
PH Marina · Budget
40
PH Marina · Customer
30
PH Marina · Legal
55
Enugu · Contract.
28
Enugu · Material
44
Enugu · Permit
62
Abuja · Contract.
46
Abuja · Permit
66
Abuja · Labour
60
Eko Bay · Quality
52
Eko Bay · Material
70
Magodo · Material
50
Ibadan · Utility
55
Kuje · Permit
58
Kuje · Compliance
62
Kano · Community
68
Lekki · All
88
AI FORECAST
Project delay probability (%)
AI forecast based on contractor pace, budget variance, permit status and resource availability.
Resource shortage tracker
Materials · equipment · labour · utilities
| Resource | Status | Owner | Estates | ETA | Action |
|---|---|---|---|---|---|
| Cement | high risk | Procurement | Magodo · PH Marina | 72h | Alternate supplier |
| Power equipment | delayed 8d | IBEDC | Ibadan · Ibeju | 8d | Escalate NERC |
| Drainage materials | blocked | Supplier | PH Marina | 5d | Alternate route |
| Labour crews | 4 short | HR | Abuja Hills | 3d | Redeploy |
| Machinery | 2 units off | Fleet | Eko Bay | 24h | Rent |
| Security install. | awaiting | Procurement | Kuje Heights | 10d | Approve PO |
PERMIT & COMPLIANCE
Permit progression · estate status by stage
Survey Approval
Drainage Permit
Power Approval
Registry Filing
Environmental
Handover Compliance
Lekki Pearl
Ibeju City
Abuja Hills
Eko Bay
PH Marina
Enugu Skyline
Kuje Heights
Magodo Vista
Ibadan Crest
cleared in-progress pending
Executive escalations
last 24 hours
PH Marina drainage · 18d behind
₦42M exposure · refund risk surfacing
Enugu Skyline land prep · 14d behind
Niger Build Group · contract review needed
Magodo Vista · cement shortage 72h
Sahel Cement supply disruption · alternate sourced
Ibadan Crest · transformer ETA +8d
IBEDC dependency · escalated to NERC liaison
Kuje Heights drainage permit pending
FCT Office · legal follow-up filed
Eko Bay road rework awaiting QA
4 sections · QA team dispatched
Lekki Pearl roads back on schedule
Citadel Build added 2 crews · recovered 4 days
Recovery plan board
Kanban view · owner + status
To review
2PH Marina contractor replacement
Enugu Skyline budget variance
In recovery
2Abuja Hills perimeter crew +2
Magodo Vista cement sourcing
Escalated
2Niger Build payment hold
PH Marina customer notification
Resolved
2Lekki Pearl road recovery
Ibeju City power inspection
Development risk impact matrix
Operational · Customer · Financial · Legal
Operational impact
PH Marina drainage
criticalprogramme risk
Abuja perimeter
highsite sequencing
Magodo cement
highsite downtime
Customer impact
PH Marina · 14 buyers
criticalrefund exposure
Enugu Skyline · 22 buyers
highhandover slip
Kuje Heights · 8 buyers
mediumcommunication gap
Financial impact
Niger Build variance
critical₦22M
Coastal exposure
critical₦42M
Lagos Build rework
high₦14M
Legal impact
FCT drainage permit
mediumregulatory hold
Coastal breach clause
hightermination path
Kano access dispute
mediumcommunity mediation
AI Development Risk Brief · 89% confidence
Top 3 risks
- PH Marina drainage delay
- Enugu Skyline land prep overrun
- Abuja Hills perimeter timeline slip
Likely delay
PH Marina may slip 9–12 additional days without contractor replacement.
Recommended intervention
Reassign drainage recovery to Sahel Construction, freeze Niger Build payments, and approve additional crew for Abuja Hills.
Responsible owner
Executive Operations Lead · CFO co-sign
Recovery progress tracker · last 30 days
Executive KPI progression
Delays recovered
on track6
/ 12
target 12
Risks closed
on track14
/ 20
target 20
Exposure reduced ₦M
watch38
/ 60
target ₦60M
Permits cleared
steady9
/ 12
target 12
Cust. escalations prevented
on track22
/ 30
rolling 30d
Estates back on track
ready5
/ 7
of 7 flagged
Action Queue
5 pendingReassign PH Marina drainage · Sahel
Ops · CFO co-sign
48h
Suspend Niger Build payments
Finance hold
12h
Approve Abuja Hills crew expansion
HR + Ops
24h
Customer comms · PH Marina
Marketing
24h
FCT permit intervention · Kuje
Legal
72h
Activity Timeline
- PH Marina · escalation to CRITICAL09:2018-day slip confirmed
- Sahel Construction pre-briefed11:05Recovery pack sent
- Niger Build payment held13:40CFO instruction · ₦42M
- Cement alt-supplier confirmed15:15Magodo Vista · 21d cover
- Customer comms brief approved17:0014 PH Marina buyers · 24h send