CONSTRUCTION · MILESTONES

Construction milestones

Timeline of contractual deliverables across all active sites

Total Milestones
62
Completed
38
In Progress
11
At Risk
4
On-time Rate
84%
Milestone roadmap · next 90 days
Sep 12
Pile foundation complete · Block A
Ibeju City · Phase 3
done
Sep 28
Phase 2 customer handover ceremony
Lekki Pearl
done
Oct 04
Seawall reinforcement layer 3
PH Marina
in-progress
Oct 18
Clubhouse structural topping out
Abuja Hills
in-progress
Nov 02
Internal road base course
Calabar Greens
scheduled
Nov 21
Phase 3 Block C topping out
Ibeju City
scheduled
Dec 15
PH Marina · seawall completion
PH Marina
scheduled
Per-project completion
Ibeju City · Phase 314/22 milestones
Lekki Pearl · Phase 222/25 milestones
PH Marina · Infra6/18 milestones
Abuja Hills · Clubhouse10/14 milestones
Calabar Greens · Roads3/12 milestones