LEKKI PEARL · PHASE 3
Estate Progress Gallery
Watch your investment take shape — month by month, milestone by milestone.
Overall Development
78%
Road Network
82%
Drainage
91%
Street Lighting
64%
Security
55%
Landscaping
22%
Utilities
69%
Construction Progress Timeline
Six months · seven categories tracked
JANUARY
Land Clearing
Jan 28, 2025
Completed
100%
Next: Earthworks · Feb
FEBRUARY
Earth Works
Feb 24, 2025
Completed
100%
Next: Drainage · Mar
MARCH
Drainage
Mar 30, 2025
Completed
100%
Next: Roads · Apr
APRIL
Roads
May 15, 2025 · est.
In Progress
82%
Next: Street Lights · May
MAY
Street Lights
Jun 10, 2025 · est.
In Progress
64%
Next: Security Gate · Jun
JUNE
Security Gate
Jul 02, 2025 · est.
Active
35%
Next: Landscaping · Jul
Cumulative Progress
Actual vs Plan · 6-month curve
Quick Stats
Days On-Site
178
+12 vs plan
Materials Delivered
92%
of phase budget
Workforce Today
142
across 4 zones
Before vs Current
Drag the slider to compare site evolution
Bare Land · Jan 2025
Current · Jun 2025
BEFORE
CURRENT
Drone Gallery
Organised by month · click any frame to enlarge
W24
W23
W22
W21
W20
W19
W18
W17
W16
W15
W14
W13
Construction Videos
Drone footage · site walk-throughs · engineer briefings
4:32
Phase 3 · Drone Survey
May 04 · Aerial sweep of Block A & B foundations.
6:11
Engineer Update · Roads
Apr 28 · Walkthrough of asphalt prep and curbing.
12:08
Allocation Ceremony 2025
Apr 14 · Owners receive plot allocation letters.
3:50
Infrastructure Recap Q1
Apr 02 · Drainage, gate house, security walls.
Infrastructure Heatmap
Current vs expected delivery
| Category | Current | Expected | Delay | Target Date |
|---|---|---|---|---|
| Roads | 82% | 90% | +8d | Aug 15 |
| Drainage | 91% | 90% | On track | On track |
| Security | 55% | 70% | +15d | Sep 22 |
| Utilities | 69% | 75% | +6d | Oct 04 |
| Landscaping | 22% | 40% | +18d | Nov 18 |
| Water | 73% | 75% | +2d | Sep 30 |
| Electricity | 61% | 70% | +9d | Oct 12 |